Milestones

Milestone Date
Build Contract signed with BAM Construction March 2018
Site mobilisation April 2018
Works commence to podium and transfer slab April 2018
Tower crane arrival on site October 2018
Structural steel work commences October 2018
Concrete slab installation begins April 2019
Topping out of steel structure August 2019
Commencement of internal finishes August 2019
Envelope works commence September 2019
Internal finishes complete and removal of tower crane March 2020
Occupiers ability to take early access for fit out April 2020
External works completed May 2020
Testing and commissioning completed May 2020
Practical Completion May 2020
Occupiers ability to take operational occupation June 2020